The pre-delivery inspection is mandatory for a building covered by the Garantie de construction résidentielle (GCR): you walk through the unit with the contractor and note on the GCR form everything to finish or fix. You then have 3 days to add an apparent defect, if you have not moved in.
GCR rules checked on November 20, 2026.
What GCR says
- The contractor provides the inspection form approved by the Régie du bâtiment; it must never be pre-filled. The acceptance boxes are for the buyer only.
- You may bring a building professional.
- You accept the building with or without reservations; with reservations, a date is agreed to finish the work, which must be done within 6 months of the inspection.
- The warranty starts when the form is signed. After acceptance: 1 year for poor workmanship that was not apparent, 3 years for hidden defects, 5 years for design, construction or production defects and soil defects.
- For a condo, the common areas are inspected on a separate form.
To check that your furniture fits the rooms before delivery, try Will my furniture fit?.
Frequently asked questions
Is the pre-delivery inspection mandatory?
Yes, for any building covered by the guarantee plan for new residential buildings, administered by GCR. Without a signed form, GCR does not issue a warranty certificate.
How long do I have to report a defect I missed?
3 days after the inspection for an apparent defect, if you have not moved in. After that, the warranty covers poor workmanship that was not apparent for 1 year and hidden defects for 3 years.
Should I hire an inspector?
It is not mandatory, but GCR lets you bring a building professional. They often spot what a buyer does not.
See this plan furnished
Open the demo project: every unit, every room, furnished in several styles, from the plan.
Open the demo →For developers
Add this tool to your project’s page, in your colours, next to the “See it furnished” module.
Add this tool to your project →Sources
Checked on November 20, 2026. The checklist items are a seee aide-memoire, not a GCR document.